PJM capacity auction hits $325 cap, 6.8 GW short

PJM's 2028/2029 capacity auction cleared at the $325/MW-day cap, procured 138,318 MW and fell 6,831 MW short of its reliability target. Data centers drove demand.

On 14 July 2026, PJM Interconnection announced that its 2028/2029 capacity auction cleared at the $325/MW-day price cap. It procured 138,318 MW but fell 6,831 MW short of its reliability requirement. The cleared supply is worth $16.4 billion. Demand from data centers is a main driver.

This article is general information, not financial advice.

What exactly happened?

PJM operates the grid and wholesale market for more than 67 million people across 13 states and the District of Columbia. It holds capacity auctions that pay power plants and demand-response providers to be available in a future delivery year.

The latest auction covered June 2028 to May 2029. The price hit the cap set with the PJM governors and FERC, a collar of floor and cap used for four auctions. This was the third in a row under the collar.

Indicator2028/2029 auction
Clearing price$325/MW-day, the cap, across the whole footprint
Change from previous capDown 2.5% from $333.44/MW-day
Capacity procured (UCAP)138,318 MW
Plus Fixed Resource Requirement areas10,864 MW, for 149,182 MW in total
Shortfall against reliability requirement6,831 MW
Shortfall in the previous auctionAbout 6,500 MW
Value of cleared supply$16.4 billion
New generation and uprates cleared525 MW
Reserve margin for 2028/202914.7%

UCAP, or unforced capacity, is a plant’s output adjusted for how reliably it performs at times of highest risk. The reliability requirement is set so that shortages occur no more than once every ten years.

Why is supply falling short?

Demand is rising faster than new supply. PJM’s forecast peak load for 2028/2029 is about 2,000 MW higher than the forecast used a year earlier. PJM links the trend to large data center loads added to its forecast.

Supply is barely moving. Offered supply rose by 3,447 MW. Gas capacity grew mainly through higher accreditation and coal-to-gas conversions. Only 525 MW of new generation and uprates cleared.

PJM’s chief executive, David Mills, said demand “continues to grow faster than electricity supply.” PJM notes that these were the first auctions in its history in which the whole region fell short.

How much do data centers cost consumers?

The auction value is $16.4 billion. PJM notes this is not the total cost to consumers, because load hedged through contracts is not exposed to auction prices.

Joseph Bowring, president of PJM’s independent market monitor, estimated that about $6.3 billion of that total was attributable to data center demand. Bloomberg’s report adds that the data center burden reaches almost $30 billion when three previous auctions are included.

The price collar softened the hit. Utility Dive reports that without it, the auction would have cleared near $555/MW-day and cost $29.7 billion. In the ComEd zone around Chicago, the uncapped price would have reached about $777/MW-day.

ScenarioPriceTotal value
With the collar (actual)$325/MW-day$16.4 billion
Without the collar (Utility Dive)About $555/MW-day$29.7 billion

What is PJM doing about it?

PJM listed several measures in its announcement:

  • A Reliability Backstop Procurement, planned for September, to address near-term shortfalls.
  • “Connect and Manage” frameworks that let large loads such as data centers connect but run flexibly when needed.
  • A temporary expedited track for up to 10 state-sponsored, shovel-ready generation projects.
  • Clearing the interconnection queue backlog, including work with Google’s Tapestry to shorten studies with AI.
  • Facilitating long-term bilateral contracts between large loads and new generation, started on 9 June.

These steps follow FERC’s 18 June orders on how grid operators connect large loads. We covered them in our note on FERC’s large-load orders.

What do skeptics say?

The collar limits prices but not the shortage. PJM itself says the cap and floor do not solve the underlying imbalance between supply and demand. Analysts quoted by Utility Dive expect similar results next time.

There is also a fairness debate. If data centers drive a large share of the cost, households and small firms help pay for growth they did not cause. PJM’s Connect and Manage and bilateral contract plans are partly a response to that concern.

What does it mean for companies and governments?

For data center developers, power is now the binding constraint in PJM. Sites with their own generation, flexible operation or long-term supply contracts will move faster.

For companies buying electricity in PJM, capacity prices are set at the cap through the 2028/2029 delivery year. Contracts and hedges matter more.

For governments, the question is who pays for growth. States in PJM must balance attracting data centers against protecting consumer bills.

How we see it at Blackwood

Blackwood Stone Holdings is an applied research and development company specialized in artificial intelligence and advanced engineering, founded in 2009. Each AI workload now carries an energy cost that grid operators can measure. We design applied AI systems to justify the compute they use. We also watch the energy sector, because power availability will shape where AI is deployed.

Frequently asked questions

What was the result of PJM's 2028/2029 capacity auction?
The auction secured 138,318 MW of capacity at $325 per MW-day, the FERC-approved cap, for the whole PJM region. Total capacity was 6,831 MW short of PJM's reliability requirement.
What is a capacity auction?
It is a market in which a grid operator pays power plants and demand-response providers to be available years ahead. PJM uses it to secure enough supply to meet future peak demand plus a reserve margin.
How much will the PJM auction cost?
The cleared supply multiplied by the clearing price totals $16.4 billion. PJM notes that this is not the total cost to consumers, because hedged load is not exposed to auction prices.
How much of the cost is due to data centers?
According to Bloomberg, Joseph Bowring of PJM's independent market monitor attributed about $6.3 billion of the $16.4 billion to data center demand.
Why did the price hit the cap?
Demand is growing faster than supply. PJM's forecast peak load for 2028/2029 rose by about 2,000 MW, and only 525 MW of new generation and uprates cleared.
Does the shortfall mean blackouts in PJM?
Not necessarily. PJM says it means operating with slimmer reserves and greater risk. It still expects a reserve margin of 14.7% for the 2028/2029 delivery year.

Sources

  1. PJM Capacity Auction Procures 138,318 MW of Generation Resources PJM Interconnection, 2026
  2. PJM capacity prices hit price cap as reserve shortfall grows Utility Dive, 2026
  3. PJM power auction falls short again as data center demand climbs (Bloomberg) Insurance Journal, 2026
A woman smiling over her shoulder, the Manhattan skyline far behind her

Bring us the toughest challenge in your operation

We will show you what we have already built for it, and how we would run it with you.

Let's solve it together