FERC orders grid operators to fix data center hookups

On 18 June 2026 FERC gave six US grid operators 60 days to justify or revise how they connect data centers and other large loads, instead of issuing a national rule.

On 18 June 2026, the US regulator FERC told six grid operators to justify or revise how they connect data centers and other large users. Each has 60 days to respond. FERC chose these targeted orders instead of the national rule the Department of Energy had asked it to consider.

This article is general information, not legal advice.

What exactly happened?

FERC issued six parallel show-cause orders under section 206 of the Federal Power Act. A show-cause order asks a regulated party to prove its current rules are just and reasonable, or else change them. It does not impose new rules by itself.

The orders went to every grid operator under FERC jurisdiction, Power Engineering reports: PJM, MISO, SPP, California ISO, ISO New England and New York ISO. Together with their member transmission owners, they must respond on two tracks.

DeadlineWhat each operator must file
Within 30 daysAn informational report on how it will ensure adequate generation for existing and new large loads
Within 60 daysEither a justification of its current tariff or proposed revisions that address FERC’s concerns

Power Engineering lists the docket as RM26-4-000. ERCOT, which runs most of the Texas grid, is outside FERC’s reach and is not covered.

What must grid operators address?

The orders set out five areas of reform, according to Power Engineering:

  1. Efficient application and study processes for transmission service to large loads.
  2. Rules that prevent costs from shifting to other customers, with cost transparency.
  3. Accommodation of co-location and behind-the-meter generation.
  4. New transmission services suited to flexible large loads.
  5. Studies of generators that serve nearby or co-located large loads.

Co-location means building a large load, such as a data center, next to a power plant. Behind-the-meter generation is power produced on site that does not pass through the utility meter. Flexible loads are users that can reduce demand when the grid is stressed.

Power Engineering also notes that each operator may define what counts as a large load in its own region.

Why did FERC avoid a national rule?

The process began in October 2025. Energy Secretary Chris Wright directed FERC to consider an advance notice of proposed rulemaking on large-load interconnection. Latitude Media reports that he proposed FERC take authority over these connections and standardize study rules. He also proposed that large loads pay all network upgrade costs.

The docket drew more than 3,500 pages of comments. FERC then took a different route. Latitude Media’s analysis is that a rulemaking would have been slow and likely to face legal challenges over federal and state jurisdiction. Show-cause orders put pressure on each operator now and leave room for regional differences.

ApproachNational rulemaking (asked by DOE)Show-cause orders (chosen by FERC)
ScopeOne standard rule for all regionsSix region-specific proceedings
SpeedMulti-stage, uncertain timelineResponses due within 60 days
Legal exposureLikely jurisdictional challengesNarrower, operator-by-operator
OutcomeUniform tariff termsTariffs justified or revised per region

FERC Chair Laura Swett called the changes “prospective reforms” that will not disrupt large-load deals already under negotiation, Latitude Media reports. Power Engineering quotes her stressing certainty for investors.

Why does it matter?

Data centers and advanced factories are asking grid operators for very large new connections. Long studies and unclear cost rules have made those connections a bottleneck. FERC’s stated aim is to speed their integration onto the grid.

The orders target that gap. Faster, standardized studies could shorten waiting times. Cost-shifting rules aim to protect households and small businesses from paying for upgrades that serve a single large customer. Flexible-load services could let a data center connect sooner if it agrees to cut demand during peaks.

What is still uncertain?

Show-cause orders start a process; they do not finish it. The outcome depends on what each operator files and how FERC judges it. Six operators may produce six different answers.

The orders also leave key tools with the states. Retail electricity service, including much of how large customers are billed, remains under state authority. Disputes over who pays for new transmission are therefore likely to continue.

Finally, faster interconnection does not create new power plants. If supply stays tight, connecting large loads sooner could raise pressure on capacity prices.

What does it mean for companies and governments?

For data center developers, the next 60 days matter. Each operator’s filing will show how long studies take, what flexibility earns, and who pays for upgrades. Site selection may shift toward regions with clearer rules.

For utilities and state regulators, the orders raise the bar for transparency. They will need to show that large customers pay their share.

For companies that buy cloud and AI services, energy access is becoming part of the cost and timing of compute. Capacity plans should consider where power is available, not only where servers are.

How we see it at Blackwood

Blackwood Stone Holdings is an applied research and development company specialized in artificial intelligence and advanced engineering, founded in 2009. AI capacity is now limited as much by grid connections as by chips. We design applied AI systems to do more useful work per unit of compute. We also follow the energy sector closely, because power will shape where AI can run.

Frequently asked questions

What did FERC order on 18 June 2026?
FERC issued six show-cause orders under section 206 of the Federal Power Act. They require the six FERC-jurisdictional grid operators to justify or revise how they connect large loads such as data centers.
Which grid operators are affected?
PJM Interconnection, MISO, Southwest Power Pool, California ISO, ISO New England and New York ISO. ERCOT, which runs most of the Texas grid, is not covered.
What is a show-cause order?
It is an order that asks a regulated party to show why its current rules are just and reasonable, or else propose changes. It does not by itself impose new rules or rates.
What are the deadlines?
Each operator must file an informational report on generation adequacy for existing and new large loads within 30 days. Within 60 days it must justify its tariff or propose revisions.
Why didn't FERC adopt a national rule for data centers?
Latitude Media reports that a rulemaking would have been slow and likely to face jurisdictional legal challenges. Show-cause orders put direct pressure on each operator and allow regional differences.
Will the orders affect existing data center deals?
FERC Chair Laura Swett described the changes as prospective reforms that will not disrupt existing large-load deals, according to Latitude Media.

Sources

  1. FERC launches aggressive, targeted action to speed large load integration Federal Energy Regulatory Commission, 2026
  2. FERC takes historic action, orders US grid operators to 'defend or revise' large load interconnection tariffs Power Engineering, 2026
  3. FERC to grid operators: connect large loads to transmission faster Latitude Media, 2026
A woman smiling over her shoulder, the Manhattan skyline far behind her

Bring us the toughest challenge in your operation

We will show you what we have already built for it, and how we would run it with you.

Let's solve it together